Mt Crosby West Bank WTP is a conventional design with sedimentation, filtration and disinfection. As the back-up supply for Mt Crosby East Bank WTP, the Plant has 12 filters that utilise Dissolved Air Flotation to assist in the removal of filter solid waste. The key purpose of this project was to improve the Plant’s reliability replacing existing hardware with the latest compliant hardware. Work included the supply, installation, and commissioning of 4 back wash motors, 16 filter inlet penstock valve electric actuators, 36 back wash inlet valves and pneumatic actuators, 10 air scour valve pneumatic actuators, 11 back wash outlet penstock valve electric actuators and 6 pure water outlet butterfly valve electric actuators.
testimonial
"The efforts of the GO team ensured that all works were undertaken in a safe, competent manner, with a quality that was second to none. I must also commend the attitude, work ethic and behaviour of the GO team on site, as it was exceptional".